Start a conversation
Home About
Services Every service
Building Custom Home Builds Luxury Home Builds New Home Construction Custom Home Design Multi-Structure Estate Construction Custom Garages Shop Buildings
Remodeling Whole Home Remodeling Home Renovations Kitchen Remodeling New Kitchen Construction Bathroom Remodeling Custom Tile Bathrooms Home Additions Exterior Remodeling Home Theater Construction
Roofing Standing Seam Metal Roofing Installation Standing Seam Metal Roofing Replacement Dimensional Shingle Roofing
Outdoor Outdoor Living Spaces Outdoor Kitchen Construction Patio Construction Custom Composite Deck Construction Covered Decks Porch Construction Aluminum Railing Installation Custom Pergola Construction Cedar Pavilions Covered Bridges Residential Bridges
Water Custom Pool Construction Hot Tub Installation Water Features Custom Waterfalls
Sitework Retaining Walls Excavation Services Decorative Concrete Stamped Concrete Patios Stamped Concrete Sidewalks Concrete Driveways
Finishes Custom Tile Installation Tile Shower Installation Interior Stonework Stone Veneer Installation Granite Countertops Quartz Countertops Custom Carpentry Custom Woodworking Interior Painting Premium Exterior Painting
Areas Every area
Montgomery County Montgomery County Oakwood Miamisburg West Carrollton Trotwood Englewood Vandalia Clayton Germantown Brookville New Lebanon
Greene County Greene County Beavercreek Xenia Fairborn Bellbrook Yellow Springs Cedarville Jamestown Spring Valley
Warren County Warren County Springboro Lebanon Mason Franklin Monroe Waynesville Carlisle Maineville
Butler County Butler County Hamilton Fairfield West Chester Oxford Middletown Trenton Liberty Township
Preble County Preble County Eaton West Alexandria Lewisburg Gratis Camden West Manchester
Miami County Miami County Troy Piqua Tipp City West Milton Covington Pleasant Hill
Gallery Blog Contact Call · (937) 818-6177
Skip to content

Replacing a One-Car Garage Starts at the Slab

November 2026

A lot of the older houses in Kettering were built with a one-car garage, and some with no garage at all. Families outgrow that quickly. When someone calls us about tearing out a single bay and putting up a detached two-car garage, we start at the ground. A garage is a small building with most of the same needs as a house, and nearly all of the ones that decide how long it lasts sit underneath the slab, long before a single stud is cut.

Taking the old garage down without hurting the lot

Demolition is the fast part. What matters more is what the machines do to the rest of the yard on their way in and out. We plan the route for equipment before anything arrives, protect the roots we can and get the gas, water and power lines marked so a bucket never finds one by accident.

The old slab almost always goes too. Single-car garages from that era were often poured thin, straight onto the dirt, and by now many are cracked and tipped toward the door. Pouring new concrete over an old slab only copies its problems a few inches higher. Once it is broken out and hauled away, we can see the soil underneath, dig out anything soft or full of old debris and start the new base on firm ground. That look at bare dirt is the first real information the job gives us, and it shapes every step after it.

Gravel, rebar and edge forms before any truck pours

A slab is only as good as the layer under it. We spread crushed gravel in lifts and compact each one, because a thick layer dumped all at once and packed from the top stays loose at the bottom and settles later. The gravel also lets water drain away from the underside of the concrete instead of sitting there to freeze and push up.

Edge forms come next, set to the exact height and slope the finished floor needs. A garage floor should fall gently toward the door so meltwater off a snowy car runs out rather than pooling in a back corner. Inside the forms, rebar goes down in a grid and sits up on chairs, small supports that hold the steel in the middle of the slab’s thickness. The concrete has to wrap around the steel to put it to work. Where the walls will stand, the edges are often thickened to carry the building. Where the permit calls for it, the steel is inspected before the pour.

Meeting the drive you already have

Most of these jobs keep the existing driveway, at least in part, which means the new apron has to meet old concrete at the right height. If the new slab sits even a little high, the joint becomes a lip that catches shovels and plow blades. If it sits low, water from the whole drive heads straight for the garage door. We shoot elevations on the old drive before the forms go in and set the new floor so water keeps moving away from the building.

A wider garage usually wants a wider approach, and on most lots the shape of it matters. A curved apron that sweeps off the existing drive lets a car turn in without cutting across the lawn. That curve is formed by hand with bendable form boards, and the joint between new and old concrete gets an isolation strip so the two pieces can move separately through freeze and thaw. Around the building, we grade the soil to fall away on every side. On a smaller lot, the water has to go somewhere planned, not simply downhill toward the fence line.

Walls, trusses and wrap before the siding goes on

With the slab cured, the walls go up on treated sill plates bolted down to the concrete. We frame each wall flat on the slab, stand it, plumb it and brace it, and then the roof trusses arrive. Trusses come built to the pitch on the drawings, and a carpenter sets them one at a time across the top plates, spaced and braced so they cannot rack while the roof sheathing goes on. A pitch that matches the house is one of the quiet details that makes a new garage look like it was always there.

Sheathing closes the walls, and house wrap goes over it, lapped so upper courses overlap lower ones and any water that slips behind the siding runs down and out. Door and window openings get flashed before trim. Only then does siding go up, matched to the house as closely as the materials allow, down to the reveal of the boards and the width of the corner pieces. That order is how a custom garage in Kettering comes together, with our own crew on it from the slab to the shingles.

A garage being framed on a new slab, with a carpenter setting roof trusses above open stud walls
A garage framed on a new slab, with a carpenter setting the roof trusses over open stud walls.

Power, lights and the door opening, settled early

The overhead door is the largest opening in the building, and its header has to be sized before the walls are framed. People change their minds about the door more than anything else, so we settle it on paper first: one wide door or two singles, how tall, and whether a larger vehicle might live there someday. Changing it after framing means taking the wall apart.

Electrical gets the same early attention. Before siding or drywall closes a wall, we want to know where the opener plugs in, where the outside lights hang beside the door, how many outlets a workbench needs and whether a circuit should be run now for a car charger later. Feeding power from the house to a detached garage is a trench job, and it is far easier while the yard is already open for the slab and grading. Lights by the door earn their keep on most lots, where the walk from the garage to the back door stays dark through much of the winter.

Setbacks, matching and the permit

Can the new garage sit where the old one did?

Not always. The rules on how close a building can stand to a property line may have changed since the original garage went up, and a bigger footprint can push past what is allowed. We check the setbacks against the lot before anything is drawn, so you learn the answer on paper instead of after demolition. Sometimes the fix is to turn the building or shift it on the lot.

Will it match the house?

It can, and most owners want it to. We match the roof pitch, the siding profile, the trim widths and the color as closely as the materials allow. On an older house the exact siding may not be made anymore, so we choose the nearest profile and paint it to tie in. Some owners would rather have a deliberate contrast, which we are glad to draw too.

Who deals with the permit?

We do. We pull the permit for the garage and schedule each inspection as the work reaches it. You will not be calling a building department or waiting at home for an inspector. If an inspector asks for a change, we handle it and explain what it means for the job.

Bring us the sketch

Draw the garage you picture on whatever paper is handy, and rough is fine. We will walk the lot with you, measure the drive and the setbacks, and hand you a written scope that says what is included and what is not before the old building comes down.

Call (937) 818-6177, or send a note through the contact page. The custom garages page covers the range of what we build, and the gallery has finished projects.